Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.
Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.
ACTIVITY ON TRACK AND PLATFORMS
The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.
The contractor continues to install temporary lighting and public address system infrastructure under the new steel structure. In the coming weeks, these temporary systems will become operational, and the existing platform canopies will be removed during the overnight shifts.
A second crane, located between the station and the Post Office (adjacent to Track 13), is erecting the east side of the expanded bus terminal. Due to this work, Track 13 is currently out of service for the next few months.
In the Tower Work Zone, excavation work continues, along with the installation of the remaining drilled micropiles. Customers may hear and experience vibrations from the work.
Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line.
ACTIVITY IN ATLANTIC AVENUE AREA
A crane located in the Atlantic Avenue Work Zone is currently erecting a steel structure for the new bus terminal expansion and parking garage overbuild.
The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.
Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.
ACTIVITY IN SUMMER STREET PLAZA AREA
Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line.