Construction Update - April 22, 2022

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • In the next few weeks, the existing platform canopies will be removed during the overnight shifts.

  • Over the coming months, crews will be working at night in the railyard to begin fireproofing installation. This work may modify the paths of travel at the ends of the tracks during the overnight hours.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is erecting the east side of the expanded bus terminal. Due to this work, Track 13 is out of service for the next few months. This crane will be demobilized in the coming weeks, and a smaller crane will take its place to complete the steel erection over Track 13 this fall.

  • In the Tower Work Zone, work has commenced on the concrete foundation for the tower. This concrete cap beam is expected to take 6 to 8 weeks to complete.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line.

ACTIVITY IN ATLANTIC AVENUE AREA

  • The large crane on Atlantic Avenue has been demobilized, and a smaller crane is now in its place. This crane continues to erect the steel structure over the railyard. This smaller crane will leave the site within the next few weeks to make way for foundation work in the Atlantic Avenue Work Zone. The smaller crane will return to the site later this year to complete the steel erection during daytime hours.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line.