Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.
Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.
UPCOMING ACTIVITY ON TRACK AND PLATFORMS
The station doors that provide access to Tracks 1 and 2 are currently under construction. While they are being replaced, passengers will need to use Doors 3-8 to access the outdoor concourse and platforms.
The contractor has begun work on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area. The steel erection will begin the process of covering the entire railyard.
The contractor has completed the work to shorten tracks 1 through 10. Trains on these tracks now stop approximately one to two coach lengths farther away from the sliding entrance doors to the station. The contractor will soon begin to infill a 50-foot-wide walkway across the railyard, utilizing sections of track no longer in use, which is the next step in expanding the outdoor concourse area. This will provide increased space for passenger circulation and establishment of the Tower Work Zone. Some minor adjustments to track infrastructure will be completed soon at the ends of tracks 11 & 12.
UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA
Crane assembly will begin on Friday, January 29. The contractor, working extended days (12-14 hours/day), will assemble the crane’s boom from Friday, January 29, through Sunday, January 31. The crane is expected to be operational on Monday, February 1. The assembly of the crane’s 370’ long boom will require temporary closure of two of the three travel lanes along Atlantic Avenue, as well as temporary closure of the Atlantic Avenue sidewalk adjacent to the construction zone. Access for emergency vehicles will be maintained.
During this same weekend operation, parking along the east side of Atlantic Avenue will be closed between Kneeland Street and Essex Street except for a drop-off zone just south of the Bus Terminal.
Accessible pedestrian access to the Bus Terminal will be maintained throughout the assembly of the crane.
Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.
UPCOMING ACTIVITY ON THE OUTDOOR OVERHEAD CANOPY
The canopy structure has been demolished, with the exception of a portion of a single beam that runs along the headhouse wall. This beam is being removed at night over the next few weeks. Passengers may experience re-routing around temporary work areas at night while this work is being completed.
UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA
Work in this area is being performed behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.
UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE
Work in this area is being performed behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.