Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.
Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.
UPCOMING ACTIVITY ON TRACK AND PLATFORMS
Construction on the station doors that provide access to Tracks 1 and 2 is expected be complete on Monday, March 1. In their place, a series of bifold doors will provide better access to the outdoor concourse and platforms.
The contractor has completed work to shorten Tracks 1 through 10. Moving forward, trains on these tracks will stop approximately one to two coach lengths farther away from the sliding entrance doors to the station. The contractor has begun to infill a 50-foot-wide walkway across the railyard, utilizing portions of the sections of track no longer in use, which is the next step in expanding the outdoor concourse area. This will provide increased space for passenger circulation and establishment of the Tower Work Zone. Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.
In the coming weeks, once track infill work is complete, the work zone near Tracks 9 and 10 will begin to expand. The work zone will be established sequentially over several months, beginning with the closing of Doors 7 and 8. When the zone is fully established, passengers will use the new bifold doors to access the outdoor concourse and platforms.
The contractor has begun work on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area. The steel erection will begin the process of covering the entire railyard.
UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA
The new crane, located in the Atlantic Avenue work zone, has begun to erect the steel structure for the new bus terminal expansion and parking garage overbuild.
The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.
Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.
UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA
Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.
UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE
Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.