Construction Update - January 26, 2024

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

A gallery of progress on the steel overbuild from December 2021 to January 2024.

ACTIVITY RELATING TO THE OVERBUILD STRUCTURE

  • The overbuild structure supports the expanded bus terminal and currently covers Tracks 1-13.

  • Building enclosure work and interior fit out of the overbuild structure continues above the track level.

  • Crews continue to work at night in the railyard to install support for the platform lighting, PA, and Variable Messaging System, along with electrical conduit between various tracks. This work may modify paths of travel at the ends of tracks during overnight hours.

  • Crews continue to install metal between the tower and the new overbuild structure.

TRACK 13 WORK ZONE ACTIVITY

  • Crews continue metal panel installation, concrete column enclosure work, and platform lighting and PA installation at Track 13. Due to this work, Track 13 is occasionally out of service at night along with minor service impacts during the day.

TOWER WORK ZONE ACTIVITY

  • The Tower Work Zone area at the ends of Tracks 5, 6, 7 and 8 has been modified and the paths of travel for pedestrians have been altered in this area. This condition will remain in place for approximately three months.

Graphic showing the modified Tower Work Zone, which was implemented at the end of December.

  • In the Tower Work Zone, crews continue to construct the tower superstructure and install the glass curtain wall on the exterior of the tower.

Photo taken on January 23, 2024, showing the construction proceeding above the top of the headhouse concourse area.

SUMMER STREET PLAZA ACTIVITY

  • Work in Summer Street Plaza continues behind construction barriers. This area serves as the main access point for Tower Work Zone construction. A uniformed police officer is stationed in the area when the gate is in use. 

ATLANTIC AVENUE WORK ZONE ACTIVITY

  • Crews continue to construct the remaining components of the building enclosure and foundations within the Atlantic Avenue Work Zone.

  • Eversource is performing daytime work outside the Atlantic Avenue Work Zone, which may modify pedestrian paths around the site.

REMINDERS

  • Pedestrian travel routes will be maintained and clearly delineated at all times. There will be access to CharlieCard validators used for the Fairmount Line. 

  • Commuters traveling between the South Station Concourse and the South Station Bus Terminal are encouraged to use the Platform A walkway adjacent to Track 1 to bypass the Atlantic Avenue Work Zone.