Photo taken on February 27, 2025, showing the new Great Space and archways.
Sliding door access is now available between the terminal and concourse at the ends of Tracks 5-10 to accommodate the new work zones. The Atlantic Avenue ramp and stairway provide additional accessible routes to the concourse.
We encourage passengers to wait for their trains by the new informational digital display in the Great Space instead of congregating at the ends of the tracks, adjacent to construction work zones.
Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.
Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.
Photo taken on July 10, 2025, showing the concourse area.
Activity in Tower Work Zone
Additional concourse space has been opened up, along with sliding doors at the ends of Tracks 1-4.
ACTIVITY RELATING TO THE OVERBUILD STRUCTURE
The overbuild structure supports the expanded bus terminal and currently covers Tracks 1-13.
Building enclosure work and interior fit out of the overbuild structure continues above the track level.
Crews continue night work in the railyard to install platform lighting, the PA and Variable Messaging System, plumbing piping, and insulation between various tracks. This work may modify paths of travel at the ends of tracks during overnight hours.
TRACK 13 WORK ZONE ACTIVITY
Crews have completed the majority of construction work adjacent to Track 13, including final paving. Remaining work, such as metal panel installation is ongoing. Due to this work, Track 13 is occasionally out of service at night.
SUMMER STREET PLAZA ACTIVITY
Pedestrian access from Summer Street to the South Station Concourse has been closed to reconstruct the Summer Street Plaza. The Plaza is expected to reopen in August.
Photo taken on July 10, 2025, showing construction proceeding above the top of the headhouse concourse area.
ATLANTIC AVENUE WORK ZONE ACTIVITY
Crews continue to construct remaining components of the building enclosure, landscape, and hardscape elements along Atlantic Avenue. A portion of the newly constructed sidewalk along Atlantic Avenue has been reopened for pedestrians.
Photo taken on July 10, 2025 showing re-opened Atlantic Avenue.
REMINDERS
Pedestrian travel routes will be maintained and clearly delineated at all times. There will be access to CharlieCard validators used for the Fairmount Line.
Commuters traveling between the South Station Concourse and the South Station Bus Terminal are encouraged to use the Track 1 platform to bypass the Atlantic Avenue Work Zone.