Construction Update - March 11, 2022

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • The contractor continues to install temporary lighting and public address system infrastructure under the new steel structure. In the coming weeks, these temporary systems will become operational, and the existing platform canopies will be removed during the overnight shifts.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is erecting the east side of the expanded bus terminal. Due to this work, Track 13 is currently out of service for the next few months.    

  • In the Tower Work Zone, excavation work continues, along with the installation of the remaining drilled micropiles. Customers may hear and experience vibrations from the work.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting a steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - February 18, 2022

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • The contractor has begun installing temporary lighting and public address system infrastructure under the new steel structure.  In the coming weeks, these temporary systems will become operational in preparation for the removal of the existing platform canopies, which will occur during the overnight shifts.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. This crane is erecting the east side of the expanded bus terminal.  Beginning at the end of this month, Track 13 will not be in use for the next several months. 

  • In the Tower Work Zone, the contractor completed installation of the tower’s deep foundation elements, and the heavy equipment used for that work has been demobilized. Excavation work began this week along with the installation of the remaining drilled micropiles. Customers may hear and experience vibrations from the work.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting a steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - January 28, 2022

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on January 24, 2022, showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • The contractor has begun installing temporary lighting and the public address system infrastructure under the new steel structure.  In the coming weeks, these temporary systems will become operational in preparation for the removal of the existing platform canopies, which will occur during the overnight shifts.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. Track 13 continues to operate normally during the day but is closed each night between 9:00 PM and 5:00 AM.

  • In the Tower Work Zone, the contractor has nearly completed installation of the tower’s deep foundation elements. In the coming weeks, heavy equipment currently in the Tower Work Zone will be demobilized, which will have no effect on passenger pathways. The next phase of work in this area will include excavation operations and will be entirely behind the construction barriers. Customers may hear work and experience vibrations from it.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - January 7, 2022

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on January 4, 2022, showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. Track 13 continues to operate normally during the day but is closed each night between 9:00 PM and 5:00 AM.

  • In the Tower Work Zone, the contractor continues installing the tower’s deep foundation elements. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line.

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - December 10, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on December 7, 2021, showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. Track 13 continues to operate normally during the day but is closed each night between 9:00 PM and 5:00 AM.

  • In the Tower Work Zone, the contractor continues installing the tower’s deep foundation elements. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - November 19, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on November 17, 2021, showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-11. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. Track 13 continues to operate normally during the day but is closed each night between 9:00 PM and 5:00 AM. The Track 13 overhead canopy, located between Tracks 12 and 13, is being removed, and the removal will be complete in the next few weeks. This work occurs at night.

  • In the Tower Work Zone, the contractor continues installing the tower’s deep foundation elements. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - October 29, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on October 26, 2021, showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-11, and the metal deck covers Tracks 1-9. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • A second crane, located between the station and the Post Office (adjacent to Track 13), is now in place and operational. Track 13 continues to operate normally during the day but is closed each night between 9:00 PM and 5:00 AM. The Track 13 overhead canopy, located between Tracks 12 and 13, is being removed, an operation that will take a few weeks. This work occurs at night.

A second crane, located between the station and Post Office, began operations in mid-October.

  • In the Tower Work Zone, the contractor has begun installing the tower’s deep foundation elements. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - October 8, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on October 6, 2021 showing work on the steel structure that will cover the railyard.

Photo taken on October 6, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-9. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.

  • In the Tower Work Zone, the contractor is continuing with pre-excavation operations to support installation of the tower’s deep foundation elements, which will begin in October. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • In the next few weeks, a second crane will be set up to assist with the construction of the steel structure and the expansion of the bus terminal. This crane will be located between the station and the Post Office (adjacent to Track 13). Once it is operational, Track 13 will continue to operate normally during the day, but will be closed between 9:00 PM and 5:00 AM. The overhead canopy, located between Tracks 12 and 13, will be removed in October. This work will occur at night. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane located in the Atlantic Avenue Work Zone is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone.  A uniformed police officer is stationed in the area when the gate is in use. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - September 17, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on September 14, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The next phase of steel erection has begun, and the structure (which is currently over Tracks 1-6) has begun to cover Tracks 7, 8, 9 & 10. The contractor will continue to place concrete on the new steel structure above the tracks as the structure is completed.

  • In the Tower Work Zone, the contractor is continuing with pre-excavation operations to support installation of the tower deep foundation elements, which will begin in October. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • In the next few weeks, a second crane will be set up to assist with the construction of the steel structure and the expansion of the bus terminal. This crane will be located between the station and the Post Office (adjacent to Track 13). Once it is operational, Track 13 will continue to operate normally during the day, but will be closed between 9:00 PM and 5:00 AM. The overhead canopy, located between Tracks 12 and 13 will be removed in October.  This work will occur at night. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane, located in the Atlantic Avenue Work Zone, is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. This area serves as the main construction access for the Tower Work Zone. A uniformed police officer is stationed in the area when the gate is in use.  Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - August 27, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on August 24, 2021 showing work on the steel structure that will cover the railyard.

Photo taken on August 24, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard. The next phase of steel erection has begun, and the structure (which is currently over Tracks 1-6) has begun to cover Tracks 7 and 8. The contractor will continue to place concrete on the new steel structure above the tracks as the structure is completed.

  • In the Tower Work Zone, the contractor is completing pre-excavation operations to support installation of the tower foundation elements, which will begin in September. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Minor adjustments to track infrastructure at the ends of Tracks 11 and 12 have been completed. The overhead canopy, located between Tracks 12 and 13, will be removed in September. This work will occur at night.

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane, located in the Atlantic Avenue Work Zone, is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY Near Track 13/Post Office

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - August 6, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on August 2, 2021 showing work on the steel structure that will cover the railyard.

Photo taken on August 2, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard. The next phase of steel erection has begun, and the structure (which is currently over Tracks 1-6) has begun to cover Tracks 7 and 8. The contractor will continue to place concrete on the new steel structure above the tracks as the structure is completed.

  • In the Tower Work Zone, the contractor is completing pre-excavation operations to support installation of the tower foundation elements, which will begin later this month. This work will be entirely behind the construction barriers, but customers may hear work and experience vibrations from it.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Minor adjustments to track infrastructure at the ends of Tracks 11 and 12 have been completed. Future work to remove the overhead canopies located near the end of Tracks 11 and 12 will be completed at night.

ACTIVITY IN ATLANTIC AVENUE AREA

  • Work to reconfigure the crane boom, located in the Atlantic Avenue Work Zone, began last weekend (July 30), and will be completed this weekend (August 6). The work will occur Friday through Sunday.

    • The reconfiguration of the crane’s 370’ long boom requires a temporary closure of two of the three travel lanes along Atlantic Avenue, as well as a temporary closure of the Atlantic Avenue sidewalk adjacent to the construction zone, during the weekend work. Access for emergency vehicles will be maintained.

    • During the weekend operations, parking along the east side of Atlantic Avenue is closed between Kneeland Street and Essex Street except for a drop-off zone just south of the Bus Terminal.

    • Accessible pedestrian access to the Bus Terminal will be maintained throughout the reconfiguration of the crane.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway (adjacent to Track 1) to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - July 16, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo taken on July 9, 2021 showing work on the steel structure that will cover the railyard.

Photo taken on July 9, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently erecting a steel structure that will cover the entire railyard. The next phase of steel erection has begun, and the structure (which is currently over Tracks 1-6) will begin to move towards Tracks 7 and 8. The contractor will continue to place concrete on the new steel structure above the tracks as the structure is completed.

  • In the Tower Work Zone, the contractor is completing pre-excavation operations to support installation of the tower foundation elements, which will begin in August. This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Minor adjustments to track infrastructure at the ends of Tracks 11 and 12 have been completed. Future work to remove the overhead canopies located near the end of Tracks 11 and 12 will be completed at night.

ACTIVITY IN ATLANTIC AVENUE AREA

  • The contractor will need to reconfigure the crane boom, located in the Atlantic Avenue Work Zone, over the weekends of July 30 and August 6 (Friday through Sunday of both weekends).

    • The reconfiguration of the crane’s 370’ long boom will require a temporary closure of two of the three travel lanes along Atlantic Avenue, as well as a temporary closure of the Atlantic Avenue sidewalk adjacent to the construction zone, during both weekends. Access for emergency vehicles will be maintained.

    • During these weekend operations, parking along the east side of Atlantic Avenue will be closed between Kneeland Street and Essex Street except for a drop-off zone just south of the Bus Terminal.

  • Accessible pedestrian access to the Bus Terminal will be maintained throughout the reconfiguration of the crane.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while the steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - June 25, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

Photo take on June 17, 2021 showing work on the steel structure that will cover the railyard.

Photo take on June 17, 2021 showing work on the steel structure that will cover the railyard.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.

  • The contractor is currently erecting a steel structure that will cover the entire railyard. The contractor will continue the process of placing concrete on the new structure above the tracks, as the structure is completed.

  • In the Tower Work Zone, the steel sheet piles have been installed. The contractor is competing pre-excavation operations to support installation of the tower foundation elements, which will begin in August. This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Minor adjustments to track infrastructure at the ends of Tracks 11 and 12 have been completed. Work to remove the overhead canopies located near the end of Tracks 11 and 12 has begun. Future work will be completed at night.

ACTIVITY IN ATLANTIC AVENUE AREA

  • The contractor will need to reconfigure the crane boom, located in the Atlantic Avenue Work Zone, over an upcoming weekend in July. The reconfiguration of the crane’s 370’ long boom will require a temporary closure of two of the three travel lanes along Atlantic Avenue, as well as a temporary closure of the Atlantic Avenue sidewalk adjacent to the construction zone. Access for emergency vehicles will be maintained.

    • During this same weekend operation, parking along the east side of Atlantic Avenue will be closed between Kneeland Street and Essex Street except for a drop-off zone just south of the Bus Terminal.

    • Accessible pedestrian access to the Bus Terminal will be maintained throughout the reconfiguration of the crane.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while the steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - June 4, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

ACTIVITY ON TRACK AND PLATFORMS

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.

  • The contractor is currently erecting a steel structure that will cover the entire railyard. Last week, the contractor began the process of placing concrete on the new structure above the tracks.

  • The majority of the demolition work within the Tower Work Zone has been completed. Removal of subsurface obstructions will begin in June to allow for installation of the tower foundation elements.

  • This week, the contractor began installation of the steel sheet piles. This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers can use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Minor adjustments to track infrastructure at the ends of Tracks 11 and 12 have been completed. In the coming weeks, the overhead canopy located near the end of Tracks 11 and 12 will be removed. This work will be completed at night.

ACTIVITY IN ATLANTIC AVENUE AREA

  • The contractor will need to reconfigure the crane boom, located in the Atlantic Avenue Work Zone, over an upcoming weekend later this month. The reconfiguration of the crane’s 370’ long boom will require a temporary closure of two of the three travel lanes along Atlantic Avenue, as well as a temporary closure of the Atlantic Avenue sidewalk adjacent to the construction zone. Access for emergency vehicles will be maintained.

    • During this same weekend operation, parking along the east side of Atlantic Avenue will be closed between Kneeland Street and Essex Street except for a drop-off zone just south of the Bus Terminal.

    • Accessible pedestrian access to the Bus Terminal will be maintained throughout the reconfiguration of the crane.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while the steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - May 14, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

ACTIVITY ON TRACK AND PLATFORMS

  • The Tower Work Zone has been established at the end of Tracks 7 to 10, where It provides a revised pedestrian travel pathway. Doors leading to the headhouse at the ends of these tracks have been closed.

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers will need to use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

  • Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A).  While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.  The steel erection will begin the process of covering the entire railyard.

  • The contractor is continuing demolition work in the Tower Work Zone during the day and evenings.  The demolition work is intended to be complete by June.  Steel sheet piles are scheduled to be installed when the demolition work is complete.  This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it. 

ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane, located in the Atlantic Avenue Work Zone, is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the work zone while the steel erection work continues.

  • Commuters traveling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue Work Zone.

ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel routes will be maintained at all times and clearly delineated. There will be access to CharlieCard validators used for the Fairmount Line. 

Construction Update - April 23, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

UPCOMING ACTIVITY ON TRACK AND PLATFORMS

  • The Tower Work Zone has been established at the ends of Tracks 7 to 10 with a revised pedestrian travel pathway implemented.  Doors leading to the headhouse at the ends of these tracks have been closed. 

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers will need to use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has also completed the infill of Tracks 1 and 2, further expanding the platform.

Graphic Showing paths of travel once the tower work zone is fully established.

Graphic Showing paths of travel once the tower work zone is fully established.

  • Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A).  While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.  The steel erection will begin the process of covering the entire railyard.

  • The contractor is continuing demolition work in the Tower Work Zone during the day and evenings.  At the end of the month, steel sheet piles will begin to be installed. This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it. This demolition is expected to last until June.

UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane, located in the Atlantic Avenue work zone, is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.

  • Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.

UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

Construction Update - April 9, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

UPCOMING ACTIVITY ON TRACK AND PLATFORMS

  • The Tower Work Zone has been established at the ends of Tracks 7 to 10 with a revised pedestrian travel pathway implemented.  Doors leading to the headhouse at the ends of these tracks have been closed. 

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers will need to use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. The contractor has begun infilling Tracks 1 and 2, further expanding the platform. This work should be completed by mid-April.

Graphic Showing paths of travel once the tower work zone is fully established.

Graphic Showing paths of travel once the tower work zone is fully established.

  • Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A).  While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.  The steel erection will begin the process of covering the entire railyard.

  • The contractor has begun demolition work in the Tower Work Zone during the day and evenings. This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it. This demolition is expected to last until June.

UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA

  • A crane, located in the Atlantic Avenue work zone, is currently erecting the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.

  • Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.

UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

Construction Update - March 26, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

UPCOMING ACTIVITY ON TRACK AND PLATFORMS

  • The Tower Work Zone has been established at the ends of Tracks 7 to 10 with a revised pedestrian travel pathway implemented.  Doors leading to the headhouse at the ends of these tracks have been closed. 

  • The common platform has expanded around the work zone, providing direct access to all tracks. Passengers will need to use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors are now closed. In early April, the contractor will be infilling Tracks 1 and 2, further expanding the platform.

Graphic Showing paths of travel once the tower work zone is fully established.

Graphic Showing paths of travel once the tower work zone is fully established.

  • Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A).  While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.  The steel erection will begin the process of covering the entire railyard.

  • Beginning in early April, the contractor will start demolition work in the Tower Work Zone during the day and evenings.  This work will be entirely behind the construction barriers, but customers may hear the work and experience vibrations from it.  This demolition is expected to last until June.

UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA

  • The new crane, located in the Atlantic Avenue work zone, has begun to erect the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.

  • Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.

UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

Construction Update - March 12, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

UPCOMING ACTIVITY ON TRACK AND PLATFORMS

  • Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • A portion of the tower work zone has been established at the ends of Tracks 7 to 10 with a revised pedestrian travel pathway. Doors leading to the headhouse at the ends of these tracks have been closed. The bifold doors are fully operational, as well as two additional sliding doors. 

2021_SouthStation_Overbuild Edited - AL EDITS - MARCH 15 CONDITION.png
  • Beginning March 15, the common platform will expand around the work zone, providing direct access to all tracks. Passengers will need to use the new bifold doors near Tracks 1 and 2 to access the outdoor concourse and platforms. The other sets of doors will be closed.

Graphic Showing paths of travel once the tower work zone is fully established.

Graphic Showing paths of travel once the tower work zone is fully established.

  • The contractor is currently working on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area. The steel erection will begin the process of covering the entire railyard.

UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA

  • The new crane, located in the Atlantic Avenue work zone, has begun to erect the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.

  • Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.

UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

Construction Update - February 26, 2021

Suffolk Construction, the contractor for the South Station Air Rights Project, will continue daytime and overnight construction at South Station.

Please allow extra time (5 – 10 minutes) as you get used to new construction zones and paths of travel at the station. Trains might arrive and depart on a different track than what is typical. Be sure to check your track number before boarding.

UPCOMING ACTIVITY ON TRACK AND PLATFORMS

  • Construction on the station doors that provide access to Tracks 1 and 2 is expected be complete on Monday, March 1. In their place, a series of bifold doors will provide better access to the outdoor concourse and platforms.

Graphic showing the construction zone around the doors that provide access to Tracks 1 & 2 needed to create a series of bifold doors.

Graphic showing the construction zone around the doors that provide access to Tracks 1 & 2 needed to create a series of bifold doors.

  • The contractor has completed work to shorten Tracks 1 through 10. Moving forward, trains on these tracks will stop approximately one to two coach lengths farther away from the sliding entrance doors to the station. The contractor has begun to infill a 50-foot-wide walkway across the railyard, utilizing portions of the sections of track no longer in use, which is the next step in expanding the outdoor concourse area. This will provide increased space for passenger circulation and establishment of the Tower Work Zone.  Some minor adjustments to track infrastructure will be completed soon at the ends of Tracks 11 and 12.

  • In the coming weeks, once track infill work is complete, the work zone near Tracks 9 and 10 will begin to expand. The work zone will be established sequentially over several months, beginning with the closing of Doors 7 and 8.  When the zone is fully established, passengers will use the new bifold doors to access the outdoor concourse and platforms.

Graphic Showing paths of travel once the tower work zone is fully established.

Graphic Showing paths of travel once the tower work zone is fully established.

  • The contractor has begun work on the platform adjacent to Track 1 (Platform A). While this work is being completed, the pathway along the north side of the platform has been slightly narrowed and will remain uncovered until the steel erection is substantially completed in this area.  The steel erection will begin the process of covering the entire railyard.

UPCOMING ACTIVITY IN ATLANTIC AVENUE AREA

  • The new crane, located in the Atlantic Avenue work zone, has begun to erect the steel structure for the new bus terminal expansion and parking garage overbuild.

  • The lane on Atlantic Avenue formerly available for parking will continue to be used for pedestrian access around the construction zone while the steel erection work continues.

  • Commuters travelling between the South Station concourse and the South Station bus terminal are encouraged to use the Platform A walkway to bypass the expanded Atlantic Avenue construction zone.

UPCOMING ACTIVITY IN SUMMER STREET PLAZA AREA

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.

UPCOMING ACTIVITY NEAR TRACK 13/POST OFFICE

Work in this area is taking place behind construction barriers. Pedestrian travel will be maintained at all times and clearly delineated. Access to CharlieCard validators used for the Fairmount Line will also be maintained.